4.3.18Inventories

31 December 2024

31 December 2023

Materials and consumables

10

13

Goods for resale

0

0

Multi-purpose floaters under construction

27

135

Total

37

149

Multi-purpose floaters (’MPFs’) under construction relate to the ongoing EPC phase of any Fast4Ward® new build hulls. Fast4Ward® hulls remain in inventory until they are allocated to a specific FPSO contract.

The decrease of the inventory balance at year-end 2024 mainly relates to the allocation of the multi-purpose hull to the GranMorgu FPSO awarded in 2024 partially offset by the new multi-purpose hulls for use on future FPSO projects. As per December 31, 2024, the Company has two MPFs under construction (December 31, 2023: one MPF under construction).